NTPC Ltd. (NTPC) Q4 FY22 Earnings Concall Transcript

NTPC Earnings Concall - Final Transcript

NTPC Ltd. (NSE: NTPC) Q4 FY22 Earnings Concall dated May 20, 2022 

Corporate Participants:

Rajesh Majumdar — Director Research and Head-East

Anil Kumar Gautam — Director, Finance

Chandan Kumar Mondol — Director, Commercial

Unidentified Speaker —

Ramesh Babu V. — Director, Operations

Analysts:

Mohit Kumar — DAM Capital — Analyst

Puneet Gulati — HSBC — Analyst

Rahul Modi — ICICI Securities — Analyst

Subhadip Mitra — JM Financial — Analyst

Anuj Upadhyay — HDFC Securities — Analyst

Sumit Kishore — Axis Capital — Analyst

Deepika Mundra — JPMorgan — Analyst

Aniket Mittal — SBI Mutual — Analyst

Swarnim Maheshwari — Edelweiss — Analyst

Abhineet Anand — Emkay Global — Analyst 

Presentation:

Operator

Ladies and gentlemen, good day and welcome to the 4Q FY ’22 Earnings Conference Call of NTPC Limited, hosted by Batlivala and Karani Securities India Private Limited. as a reminder, all participant lines will be in the listen-only mode. And there will be an opportunity for you to ask questions after the presentation concludes. [Operator Instructions] Please note that this conference is being recorded.

I now hand the conference over to Mr. Rajesh Majumdar from Batlivala and Karani Securities India Private Limited. Thank you, and over to you, sir.

Rajesh Majumdar — Director Research and Head-East

Yes. Hi, good evening, and warm welcome to everyone. We have with us the NTPC management to present to us the Q4 and FY ’22 earnings call, headed by Mr. AK Gautam, Director Finance. I shall hand over the the proceedings to Mr. AK Gautam and then he can take us forward from there. Over to you, Mr. Gautam.

Anil Kumar Gautam — Director, Finance

Thank you, Rajesh. Yes. Very good evening to everybody. I, AK Gautam, Director Finance welcome all of you to the Q4 FY ’22 con call of NTPC Limited. NTPC continues to deliver phenomenal performance and support the nation by ensuring uninterrupted supply of power. I have with me Shri. Ramesh Babu V, Director Operations, Shri. Chandan Kumar Mondal, Director Commercial. I also have with me other key members of the NTPC team.

Today[Phonetic], the company has announced the audited financial results for the FY ’22 along with financial results for Q4 FY ’22. The key performance highlights for the financial year and quarter ended 31 March 2022 have also been disclosed on the both our[Phonetic] stock exchanges.

Operational highlights FY ’22. During FY ’22, NTPC has added 3,372 megawatt capacity to its portfolio, commercial capacity of 4,032 megawatt including 502 megawatt capacity from renewable sources was added in FY ’22. The commercial capacity of NTPC has now become 54,597 megawatt on a stand-alone basis and 68,302 megawatts for the group as on 31 March 2022. NTPC Group generated 361 billion units and recorded highest ever annual generation in FY ’22 as compared to 314 billion units in FY ’22, an increase of 15%.

NTPC stand-alone growth generation in FY ’22 is 299 billion units as compared to 271 billion units in the corresponding previous year, registering an increase of 10%. NTPC Group recorded highest day generation of 1.22 billion units on 16 March 2022.

During FY ’22, PLF of coal-based stations of NTPC was 70.74%, hedge against the national average of 58.76%, thereby maintaining a spread of almost 12%. For FY 2022, three coal stations of NTPC with Korba, Vindhyachal, and Rihand were among the top 10 performing stations in the country in terms of PLF.

NTPC Group being a leader in the power sector has a strong commitment towards renewable[Phonetic] energy and would be targeting RE capacity of 60 gigawatts by FY ’32. NTPC has diversified into producing energy through cleaner and greener sources such as hydro, wind, solar and other green hydrogen solutions. Company has also forayed into a variety of business areas, including fuel cells, e-mobility and waste-to-energy. NTPC Group has already commissioned 1,852 megawatts of RE projects under EPC mode till FY ’22.

3,440 megawatts of RE projects, including ongoing projects of NTPC REL are presently under construction. Further builds of 2,830 megawatts have been 0:22:22[Indecipherable]. During the period, we have suffered losses due to grid restrictions and fuel supply. The generation loss due to grid restrictions in FY ’22 was 97 billion units as compared to 122 billion units in the previous year. The generation loss on account of fuel supply constraint was 7 billion units in FY ’22.

Now I will touch upon status of fuel supply. During the FY ’22 metallization of coal against ACQ was 92.83% hedge against 86.72% in FY ’21. Coal supply during FY ’22 was 195.63 million metric tons, including 2.47 million metric ton of imported coal.

The coal supply during the corresponding previous year was 170.24 million metric tons, including 0.92 million metric tons of imported coal. NTPC has registered a growth of over 27% in the production from its captive coal mines. Total coal production of 14.02 million metric ton was reported during FY ’22 as against 11 million metric ton in FY ’21. Cumulative expenditure of INR7,963.66 crores has been incurred on the development of coal mines till 31 March 2022.

Now I will update you on various other financial activities. Total income of NTPC for FY ’22 is INR1,20,042.43 crore as against corresponding previous year total of INR1,03,552.71 crores, registering an increase of 15.92%.

PAT for FY ’22 is INR16,111.42 crore as against INR13,769.52 crore in FY ’21, registering an increase of 17.01%. Total Income of the group for FY ’22 is INR134,994.31 crore as against corresponding previous year total Income of INR115,546.83 crore, registering an increase of 16.83%. PAT of the group for FY ’22 is INR16,960.29 crore as against corresponding previous year PAT of INR14,969.40 crore, registering an increase of 13.30%.

The performance of our JV and subsidies has been outstanding in FY ’22. Our subsidies have earned a profit of INR1,946.78 crore in FY ’22 as compared to INR1,737.60 crore in corresponding previous year, registering an increase of 12%. The share of NTPC in JV profit has increased by 49% from INR683.87 crore in FY ’21 to INR1,020.13 crore in FY 2022.

During the FY ’22, we have accounted dividend income of INR2,134.34 crore from our subsidies and joint venture companies as against INR1,274.19 crore received against during FY ’21. For FY ’22, the Board has recommended final dividend of INR3 per share at a share price of INR10 per share, subject to the approval of shareholders in the Annual[Phonetic] General Meeting.

As you are aware, interim dividend for FY ’22 at the rate of 40% of the paid-up share capital, that is INR4 per share has already been paid in February 2022. The regulated equity as on 31st March ’22 for NTPC stand-alone and group was INR70,890 crore and INR91,054 crore, respectively. We expect our regulated equity to grow at a double-digit CAGR over the coming years based on the capacity already under construction, making NTPC a compelling investment pick

Gross block and capital work-in-progress of NTPC limited. The gross block has increased by INR26,833.54 crore to INR2,38,390.91 crores as at 31 March 2022. And on group level, gross block has increased by INR35,431.48 crore to to INR3,08,125.18 crore, mainly on account of capitalization of new units.

CWIP stood at INR68,598.66 crore as of 31 March 2022 as compared to INR75,343.60 crore as at 31 March 2021. At the group level, CWIP stood at INR91,025.21 crore as of 31 March 2022 compared to INR97,404.16 crores as at 31 March 2021.

The ratio of gross block to CWIP is 3.48 in FY 2022 as compared to the 2.81 in FY ’21. We expect growth to continue further forward and believe the turnaround from CWIP to gross block would be weaker[Phonetic] because of greater mix of renewable capacity having a shorter gestation period.

Now fund mobilization. During the FY ’22, the company has signed a syndicated term loan of USD750 million with a door-to-door maturity of 10 years on 25 March 2022 with the consortium of banks. The loan is first 0:28:50SOFR[Phonetic] Secured Overnight Financing Rate[Phonetic] based floating rate of loan. During FY ’22, NTPC Renewable Energy Limited has signed a term loan of INR500 crore with Bank of India and received a sanction for total term loan of INR2,070 crore. Average cost of borrowing for FY ’22 is 5.94% as compared to 6.24% in FY ’21.

CapEx in FY ’22. We have incurred a CapEx of INR21,035.87 crore on a stand-alone basis and total group CapEx of INR34,490.55 crore. The capital outlay for FY ’23 on a stand-alone basis has been estimated at INR22,454 crore for NTPC.

Now certain highlights about the commercial function of the company. During FY ’22, NTPC has realized INR1,16,148 crore, which is almost — more than 100% of the build amount.

During FY ’22, INR8,800.32 crore bill were discounted with the banks as against INR18,323.60 crore discounted during FY ’21. Further, the trade receivables are maintained at a level of less than 45 days of sales.

Further, I would like to list a few other highlights. NTPC Renewable Energy Limited has opened the highest domestic credit rating of AAA within one year of its incorporation. NTPC Renewable Energy Limited has been listed — have been issued letter of intent from Government of Rajasthan for development of 10 gigawatt RE parks public projects in Rajasthan. Also, it has signed a joint venture agreement with Damodar Valley Corporation to set up ultra mega renewable energy power park and projects on reservoir and land owned by BBC.

This joint venture agreement marks the preliminary step for the formation of joint venture company with equity participation from NTPC Renewable Energy Limited and BBC in the ratio of 51:49. NTPC has signed an MoU with Energy Vault Incorporation USA for developing sustainable grid scale gravity energy storage solutions.

The objective of the MoU is to collaborate and formalize a long-term strategic partnership for deployment of Energy Vault gravity-based energy storage technology and software solutions. The technology also offers beneficial utilization of coal ash for manufacturing of composite blocks for Energy Vault gravity-based energy storage system.

Accordingly, this collaboration will promote a circular economy. NTPC is an innovative initiative [Technical Issues] provided the technology to fire[Phonetic] the waste sludge at National Capital Power Station Unit 4 boiler at Dadri. This is the first of its kind initiative in India by NTPC. The main initiative, technological solutions shall be a new step for converting STP sludge into energy in an environmental friendly way. The technology shall help in reducing CO2 emissions and, at the same time, make available a locally made alternate biofuel for boilers.

With the continued focus on clean environment, NTPC has taken up initiative of blending of green hydrogen in P&G network of GGL that is Gujarat Gas Limited at NTPC Kawas. A formal agreement between the two companies has been signed. Green hydrogen will be — will be produced by using electricity from the existing 1 megawatt floating solar project of NTPC Kawas. This will be blended with P&G in a predetermined proportion and will be used for cooking applications in NTPC Kawas township. Initially, the percentage of hydrogen blending in the P&G shall be around 5% and after successful completion, it shall be further increased.

As an environmental management initiative, flue-gas desulfurization system are under various stages of implementation and tendering for our coal-based stations. NVVN, our trading subsidy, transacted 24 billion units during the FY ’22 as against 19 billion units during FY ’21, registering a growth of 31%. This is the highest ever trading volume achieved by NVVN.

NTPC has been bestowed with the India’s best workplaces in manufacturing 2022, top 30, recognition by The Great Place to Work Institute for the fifth year in a row. NTPC been conferred excellence in prestigious CII-ITC Sustainability Award 2021 in corporate social responsibility category, twice in a row. We have also won the ATD best award 2022.

These were some of the highlights I wanted to share before we begin the question-and-answer session. Thank you.

Questions and Answers:

Operator

Thank you very much. We will now begin the question-and-answer session. [Operator Instructions] The first question is from the line of Mohit K. from DAM Capital. Please go ahead.

Mohit Kumar — DAM Capital — Analyst

Good evening, sir. And congratulations on a good set of numbers. Sir, my first question is —

Operator

Mr. Mohit, please go ahead with your question. Your line is muted.

Mohit Kumar — DAM Capital — Analyst

Hi, can you hear me? Hello. Yes. Hi. Am I audible? Hello. Hello. Am I audible?

Operator

Yes, you are.

Anil Kumar Gautam — Director, Finance

Yes. Yes.

Mohit Kumar — DAM Capital — Analyst

Yes. Hi, good morning. Good evening, sir. Congratulations on good set of numbers. So my first question is, where are we — where are we in the journey of monetization of our renewables portfolio? And are we reasonably confident of completing some transaction in this fiscal?

Anil Kumar Gautam — Director, Finance

[Indecipherable] Okay. As you know that we have already created only owned subsidy of NTPC Limited, that is NTPC Green Energy Limited. Under its umbrella, the companies like NTPC Vidyut Vyapar Nigam, NTPC Renewable Energy Limited will be there. In this company, post getting clarification from the Ministry of Power regarding taxation issues, renewable assets, which are lying in NTPC will be transferred to this company. And on getting transferred to this company, we will be going for this — either the IPO directly in the market or through some strategic investors. Yes, we are planning to have certain amount of monetization during the FY ’22-’23.

Chandan Kumar Mondol — Director, Commercial

Only, NVVN will not be there.

Anil Kumar Gautam — Director, Finance

Okay. Director Commercial just confirmed that NVVN will not be under this umbrella.

Mohit Kumar — DAM Capital — Analyst

Understood, sir. My second question is given the supply-demand situation, do you think there’ll be some revival in thermal capacity addition and we will have some role to play in the interim till the time the energy transition goes through?

Anil Kumar Gautam — Director, Finance

Okay. I will ask my ED DPM[Phonetic] to please address this question.

Unidentified Speaker —

Yes. We are going to add approximately another 5,000 megawatt of power in the days to come to augment the power requirement of the country.

Mohit Kumar — DAM Capital — Analyst

Hello.

Anil Kumar Gautam — Director, Finance

Hello.

Mohit Kumar — DAM Capital — Analyst

My question was — yes — are we going to see some sort of revival in thermal capacity addition given the shortages? Do you think the — we need to — will need to put in some more capacity in medium term?

Anil Kumar Gautam — Director, Finance

I think he has already given your question — answer that we will be going to set up another 6 gigawatt of capacity in respect of thermal power stations.

Mohit Kumar — DAM Capital — Analyst

It will be blue or — blue or it will be pure thermal capacity?

Anil Kumar Gautam — Director, Finance

It will be brown thermal capacity addition.

Unidentified Speaker —

[Indecipherable] Yes. We are planning to — we have just quoted a tender to add 2 into 660-megawatt at our old purchased[Phonetic] power system. So that is one — that is for certain that that is going to come. And it is a thermal capacity only.

Anil Kumar Gautam — Director, Finance

And apart from that, let me update Singrauli is 1,600 megawatt, Lara 1,600 megawatt and Darlipali 660 megawatt.

Mohit Kumar — DAM Capital — Analyst

Understood, sir. Thank you, sir. Thank you and all the best. Sir. Thank you.

Operator

Thank you. The next question is from the line of Puneet Gulati from HSBC. Please go ahead.

Puneet Gulati — HSBC — Analyst

Yes. Thank you so much. My first question is in respect to the quarter-on-quarter improvement in profitability, while the capacity addition was limited to about 300 megawatts. Can you talk about what has really driven this growth?

Anil Kumar Gautam — Director, Finance

I could not get. Can you repeat your question, please?

Puneet Gulati — HSBC — Analyst

Yes. I’m saying your quarter-on-quarter profitability has been quite impressive, INR41 billion going up to INR56 billion on a stand-alone basis. While the capacity addition for this quarter was only about 294 or 300 megawatt. What has driven this earnings growth?

Anil Kumar Gautam — Director, Finance

Actually, you are talking about the profit after tax, no?

Puneet Gulati — HSBC — Analyst

Yes. Yes.

Anil Kumar Gautam — Director, Finance

You know that in the previous quarter, we made certain tax adjustments under the Vivad Se Vishwas Scheme which has led to a reduced taxation of around INR2,000 crores in the previous year.

Puneet Gulati — HSBC — Analyst

Okay.

Unidentified Speaker —

In addition, I would like to add 1 more point, the capacity addition that you are talking about being added in the fourth quarter, we also have to take in account the capacity added during the entire year, if you are comparing quarter-to-quarter.

Anil Kumar Gautam — Director, Finance

And also, there are certain CRC orders which have been received during the quarter — current quarter.

Puneet Gulati — HSBC — Analyst

Okay. And what would have been the impact of those?

Anil Kumar Gautam — Director, Finance

I think impact you can — just a minute, please. Quarter-to-quarter previous year sales is around INR821 crores.

Puneet Gulati — HSBC — Analyst

Okay.

Anil Kumar Gautam — Director, Finance

Yes. That is there — other items you can obtain from Aditya Dar.

Puneet Gulati — HSBC — Analyst

Okay. The second is also, if I look at the stand-alone profit versus the consolidated profit, it seems the subsidiaries were a negative number. Can you help clarify what really happened in this quarter?

Anil Kumar Gautam — Director, Finance

It is mainly because of the stand-alone financial statement, we accounted for dividend which on a consolidated basis was eliminated.

Puneet Gulati — HSBC — Analyst

Okay. Perfect. What would be the profitability by subsidiaries, otherwise?

Anil Kumar Gautam — Director, Finance

Just a minute, please. So profit after tax from the subsidy companies is INR1,946.77 crore as against INR772.53 crore in the corresponding previous period — sorry, INR1737.60 crore in the previous quarter — previous year.

Puneet Gulati — HSBC — Analyst

Got it. That’s helpful. Thank you so much. And all the best.

Operator

Thank you. The next question is from the line of Rahul Modi from ICICI Securities. Please go ahead.

Rahul Modi — ICICI Securities — Analyst

Thank you for the opportunity. Sir, couple of questions. Sir, what would be the bidding pipeline, which you are expecting over the next 6 to 12 months in renewables that would come up? And secondly, how is the solar module market currently because I believe now with ALMM[Phonetic] coming in, we’ve got limited suppliers, so how do you see the supplies panning out?

Anil Kumar Gautam — Director, Finance

Rahul, Mohit will answer answer this question.

Unidentified Speaker —

Yes, good afternoon, Rahul. Bidding pipeline is actually guided more by SECI and MNRE rather than by us. So our expectation is that they might go ahead with bidding of around at least 10 gigawatts in the balance period of the year, if not more. On the solar module side, yes, the supply is constrained because all these factors have come together, [Indecipherable] and overall inflation in the prices. So there is inflationary pressures there. But everyone is hoping for some kind of grandfathering or something else if we release this so that [Indecipherable].

Rahul Modi — ICICI Securities — Analyst

Sir, is it causing any delays as such or do you think you are more or less comfortable in terms of time line?

Anil Kumar Gautam — Director, Finance

Some of our existing projects will face a little bit of delays, but not only because of modules, that’s also because of JV issues.

Rahul Modi — ICICI Securities — Analyst

Right, right, right. Perfect, sir. That’s very helpful. Just last question on broadly on coal availability, which obviously, we’re reading a lot in the headlines, sir, how is our coal availability currently and on the imports that we are targeting? Thank you.

Anil Kumar Gautam — Director, Finance

Mr. Babu, Director of Operations, will be —

Ramesh Babu V. — Director, Operaitons

I think right now, we have around 12 days coal available with us. And as per the government guidance, we’re also importing coal. We’ve already placed some orders and some coal has already started coming to the ports, and we are shipping them to our stations.

Rahul Modi — ICICI Securities — Analyst

Sir, what would be the price of imported coal, just to understand the trend that’s coming?

Ramesh Babu V. — Director, Operaitons

Price of the import coal is actually dependent on the index at the time of loading. So it varies when the indexes goes high, and we need to pay more. If index less, we need that less. It is linked to the index. So right now, the index is $140.

Rahul Modi — ICICI Securities — Analyst

Okay. Okay. Thank you. Thank you very much and all the best.

Operator

Thank you. The next question is from the line of Subhadip Mitra from JM Financial. Please go ahead.

Subhadip Mitra — JM Financial — Analyst

Good afternoon and thank you for the opportunity. Sir, my first question is if you could please tell us what is the adjusted PAT number for fourth quarter and full year FY ’22?

Anil Kumar Gautam — Director, Finance

If you — for the fourth quarter, it is INR4,559.98 crore as against INR3,831.01 crore in the corresponding previous quarter.

Subhadip Mitra — JM Financial — Analyst

Okay. And for the full year, sir?

Anil Kumar Gautam — Director, Finance

Full year, it could — it is INR14,700.99 crore as against INR14,218.07 crores.

Subhadip Mitra — JM Financial — Analyst

So it’s INR14,218 crore for the last year versus INR14,700 crore for the current year?

Anil Kumar Gautam — Director, Finance

Correct. INR14,701 crore.

Subhadip Mitra — JM Financial — Analyst

Okay. Understood. Sir, secondly, just to get an update on the capacity addition that we are looking at. I think if I remember the numbers correctly, as per the last call, we are looking at about close to 4 gigawatt of thermal additions in FY ’23 and a similar number for ’24 with maybe another 1.2 gigawatt of renewable. If you can just give us an update as to how much you’re seeing getting added in ’23 and ’24? And if possible, split that between thermal and renewable.

Unidentified Speaker —

Yes. Actually, we already told that we’ll be adding approximately 6 gigawatt for thermal. And also that for the — your question, which is pertaining to ’22-’23 specifically, we’ll be adding 5 gigawatts and for ’23-’24, we’ll be adding approximately 6 gigawatts.

Subhadip Mitra — JM Financial — Analyst

So if I heard you correctly, sir, you’re saying that we are adding about 5 gigawatt in FY ’23 and 6 gigawatt in FY ’24? If possible, if you can split this up between the thermal and the renewable part? How much of FY ’23, 5 gigawatt is thermal and renewable and same for ’24?

Unidentified Speaker —

Yes, in this financial year ’22-’23, which have 5 gigawatts, we renewables will be approximately 1.5 gigawatts. And for ’23-’24, it will be — the renewables will be approximately 950 gigawatts — 950 megawatt [Indecipherable] gigawatt.

Subhadip Mitra — JM Financial — Analyst

Right. So 950 megawatt in FY ’24 and 1.5 gigawatt in FY ’23, correct?

Unidentified Speaker —

Yes.

Subhadip Mitra — JM Financial — Analyst

Okay. Understood. Lastly, a question with regard to 1 of the earlier questions where we talked about some of the renewable projects, which may see delays because of issues and also because of the modules. Is it possible, sir, to quantify that how much of our capacities are getting impacted by [Indecipherable].

Anil Kumar Gautam — Director, Finance

As of now, Subhadip, I think roughly 900 megawatt is impacted by because we have to get the permission from the committee appointed by the Honorable Supreme Court, so we’re in that process, that’s about 900 megawatts.

Subhadip Mitra — JM Financial — Analyst

So sir, is this 900 megawatt included in any of the targets for FY ’23 or ’24 or these are not included?

Unidentified Speaker —

Yes, yes, yes. That is included. In fact, FY ’24 number would actually higher. But — anyway, so that is included in this chart. We are expecting to get the clearance for the next few months.

Subhadip Mitra — JM Financial — Analyst

Understood. So in case there is, let’s say, a worst-case scenario of further delay that happens with regard to the Supreme Court ruling, then the ’24 target number could get impacted. Am I right in understanding that?

Unidentified Speaker —

No, I don’t get it because if there’s a delay. Applications have already been poured. So if delay happens, these capacities get shifted to the next year. ’24 don’t seem to be impacted.

Subhadip Mitra — JM Financial — Analyst

Yes. So maybe I’m not understanding it correctly. I just wanted to understand that this 900 megawatt or 950 megawatt that we are saying the renewables which we are targeting for FY ’24 does that number get impacted in case these projects get delayed further?

Unidentified Speaker —

No, no. So it is, again, speculation, Subhadip, because when we get the approval and all these things, as of now, these numbers are what about the projects which are [Indecipherable] anything which is being awarded in this year will obviously either come next year or the year after that. So that is expected not to be impacted by the So the 900 megawatt would largely be — we expect that mostly to be commissioned this year only.

Unidentified Speaker —

Okay. Okay. Understood. So these are targeted basically for FY ’22. That’s it from my side. Thank you.

Anil Kumar Gautam — Director, Finance

Thank you.

Operator

Thank you. The next question is from the line of Anuj Upadhyay from HDFC Securities. Please go ahead.

Anuj Upadhyay — HDFC Securities — Analyst

Yes. Thanks for the [Indecipherable]. Sir, 1 clarification. The number which you quoted at 5 gigawatt, 6 gigawatt capacity addition. This is on a consol basis and not the standalone. Am I right, sir?

Unidentified Speaker —

Yes. Yes, please.

Anuj Upadhyay — HDFC Securities — Analyst

And sir, is there any fixed cost under recovery [Indecipherable] under recovery which we had booked for the current fiscal? And was this largely because of the fuel supply issue or some other [Indecipherable]

Anil Kumar Gautam — Director, Finance

Yes. During the current financial year, it is INR453 crores as against INR600 crores in the previous year.

Anuj Upadhyay — HDFC Securities — Analyst

Okay. And two things, sir, again. One, the status on the where exactly we are positioned, when we expect the project to get commissioned out there in the phase 1, firstly? And secondly, you also mentioned about the 10 gigawatt of RE, which — where we have signed LOI from the Rajasthan. So any time line by when we expect to commission? Would it happen in a phase-wise for what period of time that 10 gigawatt would get commissioned?

Unidentified Speaker —

So we intend to start the work in the next 1.5 months or so and the timeline is to commission close to around 2, 2.5 gigawatt in the next 30 months. That’s the timeline as of now. And [Indecipherable] balance capacity, you got it?

Anuj Upadhyay — HDFC Securities — Analyst

Sir, 2, 2.5 gigawatt over the next 30 months, right?

Unidentified Speaker —

Yes, yes. About 2, 2.5 gigawatts in the next 30 months, and we intend to start the work in the next 1, 1.5 months. The Rajasthan [Indecipherable] is still under discussion. In fact, we’ve had a couple of meetings with the Rajasthan officials. And they have started identification of the land which they will offer to us. So that is still too premature to talk about in terms of the capacity [Indecipherable]

Anuj Upadhyay — HDFC Securities — Analyst

Okay. Fine sir. One final clarification on this Rajasthan, the 10-gigawatt deal, sir. Does this also fall under the area where we are facing GIB issues or it’s all together different land parcel?

Unidentified Speaker —

No, no. I think you hit the nail on the head. That is exactly the reason Rajasthan government is taking a bit more time to identify the land because they don’t want it to be covered under the GIB criteria.

Anuj Upadhyay — HDFC Securities — Analyst

Okay. Fair enough, sir. Thanks. That’s it from my end.

Operator

Thank you. The next question is from the line of Sumit Kishore from Axis Capital. Please go ahead.

Sumit Kishore — Axis Capital — Analyst

Good evening, and thanks for the opportunity. My first question is for Mohit, sir, on renewables. Earlier, you had expressed that NTPC would have a 15 gigawatt renewable capacity by FY ’25. What is the scale down and realistic target now? And if you could also give us the number on the operational capacity of NTPC today? What is in stand-alone, what is in subsidiaries? And what is the total size of the portfolio, including under construction and under implementation capacity?

Unidentified Speaker —

Too many questions in one go. So I am not sure whether I remember all of them, but — okay, so we have — I think it was already mentioned by [Indecipherable] in his opening remarks. We have a 1,852 megawatt which is under operation today. In fact, that number got increased by 35 megawatt just today because we started to work on a [Indecipherable] capacity. That is the number we have today.

Your initial question regarding 15 gigawatt, obviously, this discussion was when the impact of COVID did not get factored in. To that extent, we expect there to be a delay of about 12 months in achieving this capacity because there have been headwinds in terms of getting the work issues have been there. But we are not significantly delaying for what we had stated upfront. And what was the third part?

Sumit Kishore — Axis Capital — Analyst

Yes. What is the total size of your renewable portfolio today? So we know the operational at capacity, what is the size of the under-construction portfolio right now and the under implementation of whatever you call it?

Unidentified Speaker —

Yes. So operational capacity is 18 — under construction, where the work is already in progress is about 3,400. We have about 2,800 megawatt which is under tendering. So that is pipeline as of [Indecipherable]

Sumit Kishore — Axis Capital — Analyst

And sir, you had mentioned that there was this 15 gigawatt sort of expression of interest for module sources. How has that progressed and has that got settled because the module prices have been elevated and there are uncertainties?

Unidentified Speaker —

Yes, you’re absolutely right. We had won with the UI [Indecipherable] prices have been very high. So we, in fact, intended to go ahead with the long-term sourcing of the modules. So that’s something which is held back as of now because we are waiting for some more normalization in the module prices because even the bidders are not very confident to offer a price which they will be able to hold for some time.

Sumit Kishore — Axis Capital — Analyst

Fair enough. And then it was mentioned earlier that 6 gigawatt of new coal-based capacity is going to get added I’m just wondering that with so much global opposition to addition of move coal-based capacity, which banks in India are going to fund the loan for these projects. overseas banks, I understand overseas funding will be very difficult for new thermal products?

Unidentified Speaker —

I think we will get the funding, that is [Indecipherable] six months.

Sumit Kishore — Axis Capital — Analyst

So what will be the source of funding? I’m just trying to understand.

Anil Kumar Gautam — Director, Finance

Source of funding would be from domestic sources, and we will also try for bonds from this international markets.

Sumit Kishore — Axis Capital — Analyst

Okay. Okay. Last question. What was the late payment surcharge in FY ’22 versus FY ’21? And what was the PLF incentive in FY ’22 versus FY ’21.

Anil Kumar Gautam — Director, Finance

Surcharge in FY ’22 is INR754 crores as against INR2,316 crores in the corresponding previous year. And if you want the quarter numbers also, it is — during the current quarter, it is INR161 crores as against INR620 crores in the corresponding quarter of the previous year.

Sumit Kishore — Axis Capital — Analyst

Okay and PLF incentives>

Anil Kumar Gautam — Director, Finance

Incentive is almost similar in the year 386, 399. 386 in current year as against 399 in the previous year. In quarter also almost similar, 69 in current quarter versus 45 in the previous quarter.

Sumit Kishore — Axis Capital — Analyst

Sir, what is the figure of overdue receivable at the end of FY ’22? That’s my last question.

Unidentified Speaker —

Mondol Saheb, overdue receivables.

Chandan Kumar Mondol — Director, Commercial

Just a minute. Overdue as on 31 March. Yes, it is — as on 31 March, it was INR4,274 crore.

Sumit Kishore — Axis Capital — Analyst

Okay. And this figure was about, what, INR60 billion as of FY ’21?

Chandan Kumar Mondol — Director, Commercial

Last year, it was which was INR5,660 crores.

Sumit Kishore — Axis Capital — Analyst

Thank you so much. Wish you all the best.

Operator

Thank you. The next question is from the line of Deepika Mundra from JP Morgan. Please go ahead.

Deepika Mundra — JPMorgan — Analyst

Thank you. Sir, just 2 questions. Firstly, on captive mining. What is the outlook in terms of potential for next few years — in terms of output and CapEx? And secondly, for the gas-based power plants, can you walk us through the outlook for those in terms of regulated equity recognition?

Unidentified Speaker —

Captive mining, I can only tell that last year, our capital production was 14.1 million tonnes. And FY ’22-’23, we have a target of producing approximately 26 million tonnes, which is more than 80% increase in the capacity.

And definitely, FY ’24, right now, I will not be able to tell you how much we’ll be doing it because we are in the process of awarding a new contract, new MDOs to our mines like Kerandari and Talaipalli. And if it is awarded, definitely, it will be more than this capacity of 26 million tonne that we are planning this year. And what was your second question?

Unidentified Speaker —

Gas base.

Unidentified Speaker —

Gas base. Yes. Gas base today, right now, gas price is very high. So definitely, it will be very difficult for running the gap here because most of their ECR may not be sustainable. It may not come under this [Indecipherable] dispatch. But still, we will continue to have the fixed charges because except for few capacity which some of the discounts have already surrendered, and that capacity is approximately 1,000 megawatts out of the total capacity of 6,000 megawatt capacity, 1,000 megawatt has been surrendered by various DISCOM.

But we are trying to allocate this capacity to other discounts if they are willing. And probably, government is also going to take certain stale because of the power shortage in the current scenario and there — our government is already approached GAIL to arrange the best possible gas rate on which I think most likely that [Indecipherable] is going to run this capacity on emergency basis for the grid security.

Deepika Mundra — JPMorgan — Analyst

Understood, sir. And sir, would you be able to give us the total revenue for the renewable megawatt projects, which have been operational so far for the past year?

Anil Kumar Gautam — Director, Finance

I think right now, it is not available. You can obtain this information from Aditya Dar separately.

Deepika Mundra — JPMorgan — Analyst

Okay, sir. Thank you very much.

Operator

Thank you. The next question is from the line of Aniket Mittal from SBI Mutual. Please go ahead.

Aniket Mittal — SBI Mutual — Analyst

Yes, yes. And thank you for the opportunity. Just a couple of questions for my side. Sir, firstly, just to understand on this incremental brownfield capacity addition that we’re doing in Singrauli, Lara and Darlipali. What stages of discussion are in? Has like any of the DISCOMS come forth to ask for you for these incremental capacities? And have you tied up PPAs for these incremental capacities?

Anil Kumar Gautam — Director, Finance

The — this addition we have already indicated to you that 6 gigawatt we are making. And so for as PPA —

Unidentified Speaker —

So far as PPA is concerned, for Singrauli and Lara, we are already having the consent for the PPA. We’re already having.

Aniket Mittal — SBI Mutual — Analyst

Okay. And who are the DISCOMS with which we are doing this incremental —

Anil Kumar Gautam — Director, Finance

In case of Singrauli it is Northern Region and in case of Lara, it Western Region.

Aniket Mittal — SBI Mutual — Analyst

So we’ve got to go ahead in terms of the PPAs. And these would be 25-year PPAs?

Unidentified Speaker —

PPA will not be a problem, but there are other — I mean we still have to have the environment clearance in case of Lara. I think Singruali [Indecipherable]

Unidentified Speaker —

Already available.

Aniket Mittal — SBI Mutual — Analyst

No, not in terms of fuel cells, I was asking like in terms of Singrauli and Lara. So you’re saying that the PPAs we’ve got to go ahead from the DISCOMS and these would be 25-year PPAs?

Unidentified Speaker —

It will be 25-year PPAs, definitely.

Aniket Mittal — SBI Mutual — Analyst

Okay. Okay. And so as per your estimates, sir, when do you see Singrauli and Lara coming on board? Any rough time lines that you have in mind, like when you can set up this incremental —

Unidentified Speaker —

[Indecipherable] is done.

Unidentified Speaker —

Investment approval is happened in about August and schedule is worth three months.

Aniket Mittal — SBI Mutual — Analyst

Sorry, I could not hear you, could you repeat that?

Anil Kumar Gautam — Director, Finance

What he is telling that in case of Talcher, it would be 1,320 megawatt power station, that investment approval likely to happen in August. And thereafter, for completion, it will be taking four years’ time.

Aniket Mittal — SBI Mutual — Analyst

Okay. And in case of —

Anil Kumar Gautam — Director, Finance

As far as Lara and Singrauli are concerned that NIT is yet to take place. So that NIT —

Unidentified Speaker —

Singrauli and Lara, they are under continuing — means, active discussion.

Aniket Mittal — SBI Mutual — Analyst

Okay. They’re still under discussion. Okay. Fair enough. And 1 question on the CapEx front. So if I look at the NTPC renewable energy entity in itself. Could you tell me what would be the CapEx for NTPC RE over the next 3 years and split that up between your solar capacity and green hydrogen, please?

Unidentified Speaker —

I think what we can share with you right now is the tentative numbers for the next year because beyond that, a lot of things are linked to the projects which are accorded investment approval and the working of late. So next year, tentatively, we are looking at a number of about INR8,000 crores for the [Indecipherable]

Aniket Mittal — SBI Mutual — Analyst

INR8,000 crores —

Unidentified Speaker —

Next year, meaning this — the current fiscal.

Aniket Mittal — SBI Mutual — Analyst

Okay. [Indecipherable] and just to understand on the green hydrogen front because there are some pilot projects that we have started, I think, undertaking in ordering at a couple of our plants, I think Simhadri as well were also I think looking to do at one of our other plants as well. So if you could just highlight what is the sort of CapEx that you’re looking to put over there? Any other incremental plants that we are trying to develop this on a pilot basis.

Unidentified Speaker —

Okay. Plans. So you’re right. We talked about Simhadri earlier. Other one was mentioned in the opening remarks by our Director Finance that we have signed an agreement with Gujarat Gas to blend hydrogen in natural gas, which they will supply us pipe natural gas [Indecipherable] township of NTPC.

Then the other pilot, which is already underway is at [Indecipherable] where we are doing green hydrogen plus carbon capture and convert that into green methanol, so that’s the third pilot, which is — of which partly the work has started.

Fourth, of course, is the mobility pilot, for which we intend to place the orders in the next 2 months, yes, in the next 2 months or so for the hydrogen buses as well as the hydrogen filling stations. So that as of now is a broad thing.

Aniket Mittal — SBI Mutual — Analyst

Okay. Fair enough. And in general, what would be the CapEx related to these pilot projects right now?

Unidentified Speaker —

These are basically pilot projects and CapEx numbers, of course, we can compile it separately and maybe Aditya [Indecipherable]

Unidentified Speaker —

Yes, yes. It can be given separately.

Aniket Mittal — SBI Mutual — Analyst

Perfect. So thank you for taking my questions.

Operator

Thank you. The next question is from the line of Swarnim Maheshwari from Edelweiss. Please go ahead.

Swarnim Maheshwari — Edelweiss — Analyst

Thanks for the opportunity. Sir, you mentioned about 6 gigawatt of brownfield capacity. What would be the likely CapEx over here?.

Unidentified Speaker —

It will be around and INR60,000 crores, around INR60,000 crores.

Swarnim Maheshwari — Edelweiss — Analyst

INR60,000 crores. Okay. Sir, that works out to be close to INR10 crore per megawatt. But since these are brownfield, what is it actually causing such a high cost? Because I believe greenfield is more closer to INR8 crores to INR10 crores.

Unidentified Speaker —

Yes, yes. It is because we have also to clear the areas in the greenfield project to make them available for generation of new power house, we have to ship certain assets also. But I told you approximate expenditure. It is not necessary, it will be 10 gigawatt. It can be 9 also — 8 or 9. And they will involve FGD.

Swarnim Maheshwari — Edelweiss — Analyst

Yes. So one is FGD CapEx. Okay. Okay. And sir, safe to say that all of them will be on the regulator also — only regulated, right?

Unidentified Speaker —

Yes.

Swarnim Maheshwari — Edelweiss — Analyst

That’s it from my side. Thank you. Thank you so much.

Operator

Thank you. The next question is from the line of Abhineet Anand from Emkay Global. Please go ahead.

Abhineet Anand — Emkay Global — Analyst

Yes, Thanks for the opportunity. Two things. First, I wanted to know on the thermal side, what is the amount of capacity that is going out of PPA in ’23, ’24, ’25 or a cumulative number, if you can give in the next few years?

Unidentified Speaker —

Well, I think at some point of time, DISCOM wanted that they will be exiting. Now they are asking, approaching us for the capacity, if anything is available. But unfortunately, NTPC does not have a single megawatt available to be given to anybody. So we don’t think another 4, 5 years, there will be any question of exiting around capacity by any DISCOMS.

Abhineet Anand — Emkay Global — Analyst

The gas power plant that you talked about, I think, 1,000 out of the 5,000, 6,000 that we have, those can be at risk?

Unidentified Speaker —

Yes, risk is only that we may not be getting the corresponding ROE from that — those station. Nothing — otherwise, [Indecipherable] will be very minimal. These are all old power station already. We have recovered the depreciation, et cetera. So assets — government is also rethinking how to run this gas base power plants. So they are in active discussions.

Abhineet Anand — Emkay Global — Analyst

Sure. And secondly, sir, on the FGD side, majority of the orders have been given. If you can give a ballpark number in the next 1, 2 years when everything — all this [Indecipherable] being installed, what could be the incremental CapEx from NTPC side just on FGD that would have been done?

Unidentified Speaker —

Just a minute. For FPD CapEx, we are targeting approximately INR3,400 crores for this financial year and approximately INR4,000 crores for the next financial year.

Abhineet Anand — Emkay Global — Analyst

So I mean, these are the CapEx that you would be doing, right?.

Unidentified Speaker —

Yes.

Abhineet Anand — Emkay Global — Analyst

So what I was also trying to understand combined cumulatively, what is the spend on FGD that we would have done because that will then come under our regulated part, right?

Anil Kumar Gautam — Director, Finance

It is around — it is INR29,330 crores.

Abhineet Anand — Emkay Global — Analyst

And all this by ’25, I presume, will be spent, right?

Unidentified Speaker —

Yes.

Anil Kumar Gautam — Director, Finance

Yes.

Abhineet Anand — Emkay Global — Analyst

Thanks. Those were my questions. Thank you.

Operator

Ladies and gentlemen, this was the last question for today. I would now like to hand the conference over to Mr. Rajesh Majumdar for closing comments.

Rajesh Majumdar — Director Research and Head-East

So thank you, ladies and gentlemen, for a very interactive session. And thank you to the management of NTPC for conducting this session for us. I wish all the participants goodbye, and thank you once again for attending the NTPC Q4 and FY ’22 earnings call. Thank you very much, everyone.

Anil Kumar Gautam — Director, Finance

Thank you. Thank you very much.

Operator

[Operator Closing Remarks]

Disclaimer

This transcript is produced by AlphaStreet, Inc. While we strive to produce the best transcripts, it may contain misspellings and other inaccuracies. This transcript is provided as is without express or implied warranties of any kind. As with all our articles, AlphaStreet, Inc. does not assume any responsibility for your use of this content, and we strongly encourage you to do your own research, including listening to the call yourself and reading the company’s SEC filings. Neither the information nor any opinion expressed in this transcript constitutes a solicitation of the purchase or sale of securities or commodities. Any opinion expressed in the transcript does not necessarily reflect the views of AlphaStreet, Inc.

© COPYRIGHT 2021, AlphaStreet, Inc. All rights reserved. Any reproduction, redistribution or retransmission is expressly prohibited.

Most Popular

Cochin Shipyard Ltd (COCHINSHIP) Q4 FY22 Earnings Concall Transcript

Cochin Shipyard Limited (NSE:COCHINSHIP) Q4 FY22 Earnings Concall dated May. 26, 2022 Corporate Participants: Madhu S Nair -- Chairman & Managing Director Jose V J -- Director Finance Analysts: Vastupal Shah

All you need to know about Antony Waste Handling Cell in one article

Can you guess the name of the company that was listed during the IPO frenzy in 2020 and is the second largest player in the Indian municipal waste management industry?

Demystifying the Leading Non-Ferrous Recycling Company of India

“Hey, how is the market doing today?” “Oh!, its falling tremendously since morning” I am sure news like these might be a common topic of discussion for you nowadays. Interestingly,

Top