NHPC Limited Q4 FY24 Earnings Conference Call Insights

Key highlights from NHPC Limited (NHPC) Q4 FY24 Earnings Concall

  • Load Factor
    • Generation in FY24 was 21,773 million units, 12% lower than FY23.
    • Plant Availability Factor (PAF) in FY24 was 77.6%, lower by 11% compared to FY23.
    • Q4 FY24 generation was 2,304 million units, 20% lower than Q4 FY23.
  • Financial Performance
    • Revenue from operations in FY24 was Rs. 8,405 crore, 10% lower than FY23 due to lower generation.
    • Other income in FY24 was Rs. 1,624 crore, 94% higher than FY23.
    • Other income in Q4 FY24 was Rs. 591 crore, 133% higher than Q4 FY23.
    • Net profit increased by Rs. 129 crore or 26% to Rs. 698 crore in Q4 FY24 from Rs. 569 crore in the previous year.
    • Capex for FY24 was Rs. 8,652 crore against a target of Rs. 10,857 crore.
  • Expenses
    • Generation expenses decreased from Rs. 936 crore in FY23 to Rs. 814 crore in FY24 due to lower generation and reversal of water cess earlier levied.
    • Employee cost remained almost flat, decreasing marginally from Rs. 1,300 crore in FY23 to Rs. 1,297 crore in FY24.
    • Finance cost decreased from Rs. 476 crore in FY23 to Rs. 425 crore in FY24 due to changes in interest rates and loan requirements.
    • Depreciation and amortization expenses decreased from Rs. 1,145 crore in FY23 to Rs. 1,111 crore in FY24.
    • Other expenses increased from Rs. 1,708 crore in FY23 to Rs. 2,316 crore in FY24.
  • Receivables Position
    • Trade receivables stood at Rs. 3,984 crore as of March 31, 2024, including Rs. 2,264 crore in unbilled revenue.
    • Net billed receivables were Rs. 1,721 crore after adjusting for unbilled revenue and discounted bills.
    • Net amount due as of March 31, 2024, was only Rs. 818 crore, with more than 45 days dues at Rs. 277 crore.
  • Project Updates
    • Subansiri Lower project: 3 units expected to be commissioned by March 2025, remaining by May 2026. Estimated cost: Rs. 21,248 crore, incurred: Rs. 20,834 crore.
    • Uri-II project: Targeted completion by December 2024. Estimated cost: Rs. 12,164 crore, incurred: Rs. 11,127 crore.
    • Dibang Multipurpose project: Major contracts awarded, estimated cost: Rs. 31,876 crore, incurred: Rs. 2,307 crore.
    • Updates provided on Teesta VI, Bangalore, HEP, Pakal Dul, and other projects under construction.
  • Renewable Energy
    • 1,000 MW solar project progressing well, land acquisition ongoing for 700 MW capacity.
    • Received letter of intent for 200 MW solar project in Gujarat at Rs. 2.66/unit tariff.
    • Exploring pumped storage solar projects with indicative capacity of 20,000 MW across multiple states.
  • Project Delays
    • Subansiri project delayed due to subsidence in diversion tunnel 1 and hill slope slide on Left bank.
    • Major portion of restoration works completed, but hill slope restoration ongoing.
    • Diversion tunnel 1 seepage reduced from 8-9 cumecs to less than 1 cumec.
    • Remaining diversion tunnel 1 plug work to be done after monsoon season.
    • Parbati 2 project delayed due to excavation issues, now completed.
  • Capital Expenditure
    • FY25 capex target Rs. 11,761 crore, excluding pump storage projects.
    • Breakup: Subansiri, Rs. 450 cr; Deban, Rs. 950 cr; new projects, Rs. 950 cr; solar, Rs. 1,623 cr.
    • Chenab Valley projects (Pakal Dul, Kiru, Kawar) – Rs. 3,370 cr.
    • Other projects: BSUL solar, Rs. 1,550 cr; Sikkim hydro, Rs. 1,198 cr; Rangit-IV, Rs. 464 cr; Ratle, Rs. 954 cr.
    • FY26 capex plan around Rs. 13,317 crore.
  • Cash Flows
    • Strong cash flows to meet 30% equity portion of capex from internal accruals.
    • PBDIT around Rs. 3,800 cr, depreciation Rs. 1,600 cr – cash accruals Rs. 5,400 cr.
    • After dividends, around Rs. 3,600 cr available annually for equity capex.
  • Floating Solar Power
    • Signed MoU with Norway’s Ocean Sun to identify water bodies for floating solar projects.
    • Currently executing 88 MW floating solar at Omkareshwar reservoir.
    • Exploring 300 MW floating solar at Rengali, Odisha – re-tendering after earlier bid attracted only 20 MW.
  • Pump Storage Projects
    • NHPC plans 20,000 MW pump storage capacity over next 10 years.
    • Work to start in 2 years on 5,000-6,000 MW pump storage projects.
    • These projects targeted for commissioning by FY2030.
  • Subansiri Commissioning
    • 3 units to be commissioned together in March 2025 after completing civil/hydro-mechanical works.
    • Remaining 5 units to be commissioned one by one by May 2026.
    • No possibility of commissioning 1-2 units earlier than March 2025.
  • Bursar Storage Project
    • DPR prepared in 2008, declared national project by Ministry of Water Resources.
    • Viable only if government provides grant for storage component, else tariff very high at Rs. 25-30/unit.
    • NHPC to develop if government rethinks and directs, given strategic importance of storage projects.
  • Dibang Project Status
    • Construction of roads, bridges, railroads by L&T (Package 1) ongoing.
    • Power house and tunnel works by Patel-GR Infra JV (Package 2) in progress.
    • NHPC getting ready to tender main concrete dam package.
    • All land acquisition complete.
  • EPC Tender Awards
    • NHPC preparing to award EPC tenders for Sawalkot and Dugar projects simultaneously.
    • Sawalkot tender subject to approval from J&K government and Ministry of Power.
    • Dugar tender contingent on court verdict and Himachal Pradesh granting agreed concessions.
    • Both projects likely to be awarded under single EPC package.
  • Solar Project Timelines
    • 88 MW Omkareshwar floating solar project awarded to Tata Power, commissioning by Oct 2024.
    • 300 MW Rengali project under tendering, targeted commissioning in FY 2026-27.