JSW Energy Ltd (JSWENERGY) Q3 2025 Earnings Call Transcript

JSW Energy Ltd (NSE: JSWENERGY) Q3 2025 Earnings Call dated Jan. 28, 2025

Corporate Participants:

Sharad MahendraJoint Managing Director and Chief Executive Officer

Pritesh VinayDirector of Finance and Chief Financial Officer

Analysts:

Vishal PeriwalAnalyst

Mohit KumarAnalyst

Rajesh MajumdarAnalyst

Sumit KishoreAnalyst

Nikhil AbhyankarAnalyst

Saket YadavAnalyst

Swati JhunjhunwalaAnalyst

Samarth KhandelwalAnalyst

Ritwik ShethAnalyst

Presentation:

Operator

Ladies and gentlemen, good day, and welcome to the post-result Q3 FY ’25 earnings conference call of JSW Energy Limited. [Operator Instructions]. Please note that this conference is being recorded.

I now hand the conference over to Mr. Vishal Periwal from Antique Stock Broking. Thank you, and over to you, Mr. Periwal.

Vishal PeriwalAnalyst

Yeah. Thanks, Sagar [Phonetic]. Good evening, all. First of all, apologies for the slight delay to start the call. On behalf of Antique Stock Broking, I welcome you all to the post-result earnings call of JSW Energy Limited. And from the company side, we have leadership team led by Mr. Sharad Mahendra, Joint MD; Mr. Pritesh Vinay, Director, Finance, and CFO; and Mr. Bikash Chowdhury, who is Head, Investor Relations and Strategic Finance. So as usual, we’ll have brief from the management on the quarter, gone by quarter, and then we’ll have lines open for Q&A.

Yeah, Sharad, sir, over to you.

Sharad MahendraJoint Managing Director and Chief Executive Officer

Yeah. Thank you, Vishal. Good evening, ladies and gentlemen. Thank you for joining us today. It is my pleasure to share with you all the developments and updates for the quarter gone by. The sector dynamics are evolving towards energy security as we have been seeing, meeting rising base load and peaking load demand, and the adoption of low-cost energy storage solutions to integrate intermittent renewable power. This provides a blend of opportunities for developers like us having a presence across all modes of generation and will continue to provide affordable and sustainable power.

Regarding the economy, RBI has estimated GDP growth of 6.6% in the current fiscal and a projection of 6.9% in quarter one of FY ’26, which is primarily driven by robust economic activity and expectations of higher government expenditure in coming quarters.

Before I delve into our quarterly performance, I would like to provide an overview of the current power sector landscape. The power demand for the country grew at 4.5% in the first nine months of the current fiscal. In the third quarter, we have seen a demand growth moderating at 2.7%, but we have to recall that this is on a higher base of 9.9% growth witnessed during the same quarter last year. However, structurally, we continue to expect strong power demand in the medium term. The peak demand witnessed in this quarter is 224 gigawatts in December ’24 versus last year during the same quarter, the peak demand was 220 gigawatts. Overall, for FY ’24, previous year, we have seen a peak demand reaching 250 gigawatts as compared to 243 gigawatts in the current fiscal.

In line with power demand growth, the country’s generation increased by 5.3% year-to-date in FY ’25 and 3.7% in quarter three. All India thermal PLF stood at 66.7% in the quarter as compared to 66.9% in the corresponding quarter last year. The share of intermittent renewables in the total generation stands at 12.4% during the quarter.

Talking about the generation capacity, the total installed capacity in the country has reached 462 gigawatts, and the country has added 20 gigawatts so far in this current fiscal. The total renewable capacity addition in nine months in FY ’25 stands at 19 gigawatts, dominated by 16 gigawatts of solar installations. Coming to the quarter, the net capacity addition stands at 9.3 gigawatts, which compares with the 2.9 gigawatts added last year in the same quarter. Capacity additions in the quarter were driven by a renewable capacity addition of 7.9 gigawatts, dominated by solar capacity addition of 7.1 gigawatts, while wind capacity addition was 800 megawatts during the quarter.

Moving on to the bidding activity. In the current fiscal year, the total utility-scale auction of approximately 38 gigawatts capacity were bidded, which is continuing the pace that we witnessed last year. And for quarter three, total auction that took place was 16 gigawatts. Nine months was 38 gigawatts and quarter three has seen 16 gigawatts, with a notable dominance of customised solutions of hybrid and FDRE projects.

Coming to the coal. As we speak, API 4 coal prices are currently ruling at $100 per ton as compared to an average price of $110 per ton in quarter three of FY ’25 and $116 in quarter three of FY ’24.

Within the domestic market, sufficient steps are taken to keep a robust domestic coal supply. We have seen a low e-auction premium for domestic coal procurement, especially in Odisha and Chhattisgarh.

Coming to the merchant markets, we have seen a strong volume growth. The quarter gone by witnessed approximately a 16% increase in total cleared volumes at the power exchange, while day-ahead volumes increased 14% year-on-year. The higher volumes due to higher firm power availability and better hydro generation have led to moderation in prices. The day-ahead market prices have decreased 26% year-on-year to INR3.71 per unit as compared to INR5 per unit in quarter three of last year. The higher volumes across the exchanges led to lower realization in the merchant market, which impacted the dark spreads of our short-term sales. However, our short-term realization continues to be at a premium to the average exchange prices. Having said that, we remain confident in the strong power demand in the medium term.

Regarding the acquisitions, on December 27, we announced the acquisition of O2 Power, a leading renewable energy platform with a capacity of 4,696 megawatts. This acquisition valued at INR12,468 crores, marks a significant milestone for JSW Energy. O2 Power’s assets are spread across seven resource-rich states with 2.3 gigawatts of the capacity to be operational by June ’25 and an additional 2.4 gigawatts at various stages of development. This transaction will enhance our renewable energy portfolio and our footprint in this space. As guided earlier, the additional capex of 2.4 gigawatts of under-construction and pipeline projects is expected to be between INR13,000 crores to INR14,000 crores. And along with this, this platform also comes with a total connectivity, which we see, although, are aware is a big challenge now in the country, of 900 megawatts of transmission capacity already in place over and above 4.7 gigawatts, and an additional more than 800 megawatts of connectivity is at various stages of approval. So this gives us a very good space in accelerating our capacity addition going forward.

O2 Power assets are of high quality, having a blended tariff of INR3.37 with the majority of utility-scale projects tied up with high-quality offtakers like SECI, SJVN, and NTPC. Just to give a view of this total 4.7 gigawatts at a blended tariff of INR3.37, the solar component out of this total capacity is 64%, and wind capacity is 36% of the total 4.6 gigawatts, and this blended tariff, this capacity gives INR3.37. On January 10, we have also completed the acquisition of a 125-megawatt wind project from Hetero Labs and Hetero Drugs Ltd. at an enterprise valuation of approximately INR630 crores. This portfolio has a blended tariff of INR5.22 per unit and an average remaining plant life of 15 years. Accounting for this, our installed capacity as of today stands at 8,242 megawatts.

In another strategic move, we had bid for KSK Mahanadi Power Company under IBC proceedings, and we have now received a Letter of Intent for a 3,600-megawatt thermal power plant in Chhattisgarh, near to the coal belt. As the transaction gets completed, this asset, along with O2 Power, will start generating cash flows from day one. KSK Power is one of the largest thermal power plants changing hands under the IBC process. The plant’s strategic location, fuel supply agreement, and efficient operations will ensure a reliable power supply, further solidifying our leadership in the energy sector. Currently, 95% of the operational capacity of 1,800 megawatts of KSK Power is tied up with states of Uttar Pradesh and TANGEDCO, Tamil Nadu, in long- and medium-term PPAs.

Now talking about our progress towards 10 gigawatts by FY ’25, we have fully revived the JSW Energy Utkal Limited as we are talking, formerly known as Ind-Barath Thermal Power Plant, by synchronizing the second unit of 350 megawatts on January 15. We are on track to reach 10 gigawatts of capacity by end of FY ’25. In the quarter gone by, we have added 377 megawatts of capacity to our organic renewal projects, which is entirely wind and represents 47% of the country’s wind capacity addition of 800 megawatts in the third quarter. We are currently constructing 1.1 gigawatts of wind projects for SECI and Group Captive, and our Kutehr hydro plant of 240 megawatts capacity is progressing well for commissioning in the current fiscal FY ’25 only.

Now to give the update on projects beyond the 10 gigawatts, to reach 20 gigawatts before FY ’30, our total under-construction capacity stands at 7.8 gigawatts, which is beyond 10 gigawatts I’m talking, with signed PPAs, and we have 3.9 gigawatts of capacity we are — where we are expecting PPAs to be signed soon. In addition, we have 8.3 gigawatts of capacity of transactions under acquisition, of which bolt-on capacity is approximately 4 gigawatts. With all of the above, our locked-in generation capacity is now 28.3 gigawatts.

On our energy storage projects, our SECI Battery Energy Storage project of 1 gigawatt-hour, where CERC has not allowed the tariff adoption, is currently on hold. To provide some background, the project bidding was conducted transparently and in accordance with the bidding guidelines of the Ministry of Power on August 25, 2022, where JSW emerged as the L1 bidder in the e-Reverse auction. There were a total of eight developers, and we were issued a Letter of Award in January ’23. The fixed capacity discovered was INR10.8 lakhs per megawatt per month, which includes the VGF, the viability gap funding, which was being provided for this project by the government.

The project, being the first of its kind, was on a BOOT basis after 12 years, with a residual battery capacity of not less than 75% [Phonetic] of the project capacity. The developer, i.e., JSW Energy, had no guaranteed offtaker for 40%. As per the arrangement, SECI was to execute a Battery Energy Storage Purchase Agreement with the BESS developer identified through bidding, and a Battery Energy Storage Sale Agreement with the end procurer on back-to-back basis.

In March ’24, the company signed a Battery Energy Storage Purchase Agreement for the first project of 500 megawatt-hour, 250 x 2, out of the allotted 1,000 megawatt-hour. However, on January 2, 2025, current year, CERC, in its order, has not allowed tariff adoption, observing that the proposed tariff is not aligned with the prevailing market prices due to a delay by SECI in signing the Battery Energy Storage Purchase Agreement and the Battery Energy Storage Sale Agreement. We have appealed against the order in APTEL, and we are confident that this will be looked because there are a lot of precedents in this area of such tariff adoptions — tariffs being adopted earlier. So we have appealed, and we are waiting for the outcome.

In storage, our PSP project that we won in October ’24, where we were constructing 12 gigawatt-hour of pump storage plant at Bhavali in the state of Maharashtra, which is tied up with MSEDCL. We have signed the PPA. We have 48 months starting in October ’24 to complete the project. The energy storage facility agreement is for the supply of energy storage capacity for a period of 40 years, where the company will be entitled to receive a fixed capacity charge of INR84.66 lakhs per megawatt per year.

Coming to the operational performance of the quarter. Our net generation for the quarter rose by 10% year-on-year to 6.8 billion units, driven by an 18% year-on-year increase in renewable generation. This was driven by RE capacity additions and higher thermal generation. Total net generation from the tied-up portfolio was up by 7% year-on-year in the quarter, while short-term generation, including hydro, increased strongly by 28% year-on-year.

Coming to our thermal, the net generation increased 8% year-on-year, driven by the contribution of 571 million units from JSW Energy Utkal Unit 1. Our long-term thermal generation was up 4% year-on-year, while our short-term generation increased 23% year-on-year. The average PLF of our thermal assets stands at 72% as compared to the country’s average thermal PLF of 66.7%. Our renewable generation increase of 18% year-on-year was particularly driven by the addition of 928 megawatts of wind capacity in the last 12 months and a robust 14% year-on-year increase in hydro generation due to better hydrology.

Thank you, friends. With this now, I will pass on to Mr. Pritesh Vinay, CFO and Director, Finance, to talk on the financial performance for the quarter. Thank you very much.

Pritesh VinayDirector of Finance and Chief Financial Officer

Thank you, Sharad. Very good evening to all the participants who have joined us for the third quarter and nine months results conference call. Picking up a thread from what Sharad said, while the overall generation was up by 10% Y-o-Y, the total revenue was largely flattish, and the primary reason for this was that the incremental sales from the new RE capacity addition and the Utkal Unit 1 were offset by both lower short-term realization at the Ratnagiri and Vijayanagar plants as well as a lower tariff at hydro plant because of the change in depreciation policy as per the CERC tariff regulations.

The EBITDA for the quarter stood at INR1,115 crores, which was down by 9% Y-o-Y. What has also happened during the quarter is that we have commissioned about 377 megawatts of incremental wind capacity, and this capacity has come in basically post the peak season of the monsoon period.

Operator

Sorry to interrupt, sir. Sir, you’re sounding a bit distant right now.

Pritesh VinayDirector of Finance and Chief Financial Officer

Yeah. Is this better?

Operator

Much better, sir. Please go ahead.

Pritesh VinayDirector of Finance and Chief Financial Officer

Yeah. I was saying that we have commissioned 377 megawatts of wind capacity during the quarter, which has come in post peak generation season. Typically, it has come in a lean season and that too was not available for the entire 90 days of the quarter. So there’s been additional capitalization due to new capacity commission, which has led to the finance cost and the depreciation going up. As a result, the profit before tax was down and the reported profit after tax for the quarter stood at INR168 crores, which is down by 27%. If you look at the nine-month performance, the revenue was largely flattish, but the EBITDA also marginally grew largely flattish at about INR4,600 crores, and the profit after tax for the nine-month period stood at INR1,543 crores, which is up by about 12%.

Talking about the balance sheet, as the company continues to grow and invest additional amounts towards capex, the net debt at the end of December stood at about INR26,500 crores with the cash and cash equivalents just shy of INR5,000 crores. This is a sequential increase in net debt by about INR1,575 crores. The leverage ratio continues to be healthy. We reported a net debt to TTM EBITDA of 4.5 turns. Because of the additional capitalization, what has happened is that the debt on the operating companies has now gone up by about INR3,000 crores. And so excluding the capital work in progress, which was about INR10,200 crores of net debt due to capital work in progress, the net debt on the operating company stood at INR16,250 crores and this translated to a net debt to EBITDA of 2.8 times.

The weighted average interest cost inched up marginally due to the annual resets of some of the facilities and the increase in the MCLR by some of the lending institutions, but still stayed well below 8.9% at the end of the quarter. From a receivables profile, again, pretty much in control. We reported total receivables of INR2,500 crores at the end of December. The days sales outstanding, including the amount not due, stood at about 96 days. A large part of the overdue at the end of December has been received in the month of January.

That is a broad from a financial metrics point of view. I think I’ll stop there. And operator, we can open the floor for Q&A, please.

Questions and Answers:

Operator

Thank you very much. We will now begin the question-and-answer session. [Operator Instructions]. Our first question comes from Mohit Kumar from ICICI Securities. Please go ahead.

Mohit Kumar

Yeah. Thank you, sir. Thank you for the opportunity. My first question is, how do you think about the leverage given the two large acquisitions and a very large pipeline of under-construction assets?

Pritesh Vinay

So Mohit, a good question. I’ll repeat what we have consistently been maintaining for the last couple of years since we embarked on this growth journey that the strategic priority is to protect the credit ratings and whatever growth opportunities we want to pursue, we would ensure that we are well within the guardrails from a credit metrics point of view to protect the credit ratings. Especially, since you asked that in the question, I would like to reiterate and bring to everybody’s attention that after what you’re calling as two very large acquisitions, which I completely agree with, even after that, if you look at the flash put out by the credit rating agencies at the end of December, the rating agencies are comfortable maintaining our AA with a stable outlook after digesting in these two large acquisitions, because what is probably getting under-appreciated is that these two large acquisitions are also coming with large EBITDA. It is not just adding to the leverage, but it is also adding to the EBITDA. So, from an overall ratio point of view, we would be comfortable.

Of course, we’ve also rightly mentioned about the organic growth pipeline as well. And hence, if you recall about a year ago, same time, we were talking about acceleration of the growth because of a very conducive returns environment. And hence, in order to prepare ourselves better, we had gone ahead and raised capital and equity capital raise at the start of the fiscal year. It was precisely with this intention to build a war chest and ensure that the balance sheet is healthy to protect the growth.

So, I just want to reiterate that, that yes, large acquisitions, but coming with strong EBITDA generation and cash flow generation profile, and we will give strategic priorities to protect the ratings.

Mohit Kumar

Understood. My second question is on the KSK Mahanadi. What is the plan here? Is there a plan to expand capacity by one unit or more than one units in the medium term? And what is the status of NCLT for the other SPV, I think the all the SPVs are under NCLT, right, water and rail? Can you please help us with that?

Sharad Mahendra

See, this process is already on. As you rightly said, the other two SPVs also are in NCLT, and processes are at an advanced stage. So, all those things have been accounted when we have gone for this.

Regarding KSK Power, we would like to say that this is already at NCLT and the hearings are likely to take place soon, and we expect a faster earlier decision on this.

Regarding the capacities, the balanced capacities, what we are talking, we’ll just like to highlight that the operational capacity which is 50% of the total, which is 1.8 gigawatts, is fully operational tied up. Balance capacity, we have to recall that, I’ve earlier also said that most of the balance of plant is complete, whether it is power evacuation, whether it is water pipeline or running the plant, everything is ready for entire 3.6 gigawatts plant capacity. And also, for the balance 1.8 gigawatts expansion, significant part in one of the units has already been done and other two also part work has been done. So, we are quite confident the one positive, which is there is that the balanced capacity increase to take it to entire 3.6 gigawatts operational, it will be significantly lower than the benchmark cost of setting up a new greenfield capacity. So that is there and that we will be planning as and when the IBC process gets completed.

Mohit Kumar

Understood. Thank you and all the best.

Operator

Thank you. The next question comes from Rajesh Majumdar from B&K Securities. Please go ahead.

Rajesh Majumdar

Yeah, good evening, sir, and thanks for the opportunity. Sir, my question was — first question was on recent CERC order, which actually does not pay for the infirm power. This is dated Jan 23rd, and this actually does not pay for the infirm power between the time of commissioning of a plant and the commercial generation. Since Ind-Barath 2 has just been commissioned, as well as we have so much of thermal capacity additions coming in KSK Mahanadi, including capacity additions, what is the kind of impact that you envisage on this? And B, do you think it can change?

Sharad Mahendra

See, yes, this new regulation which has come, it is not going to have any significant impact because we have to see what it says that there is a ramp-up of the unit. And whenever we are working on the project, the entire process, there has — in case of Ind-Barath, there has been a very good learning while ramping up to full capacity, the first unit. And we are in a position to ramp this unit to full capacity and demonstrate for 72 hours. So, it will not take significantly long time, and we are confident that we will be reaching this capacity at much earlier timelines keeping in mind the learnings from Unit 1. So it is not going to have any significant impact. And whatever we capitalize in terms of before we do the COD, everything is well within the budgeted numbers what we have planned and budgeted for this commissioning and up to COD.

So this is well in control. And in the same process, we will be followed whenever we go for the COD commissioning and COD. So if it is a very large timeline to stabilize the unit and reach the full capacity to demonstrate, I don’t see that any significant challenge in that. We have done the evaluation ourselves.

Rajesh Majumdar

Sir, what about the project in the NCLT, KSK Mahanadi? Do you think that, that will be a problem in the new 1,800 megawatts that you envisaged because those will take much longer in terms of between the date of commissioning and the COD?

Sharad Mahendra

No, the balance 1.8 gigawatts, what you are talking?

Rajesh Majumdar

Yes, that’s right.

Pritesh Vinay

No, no, Rajesh, see, the first priority is to get the assets in our fold, right? I mean, I would request not to put the cart before the horse because first, we need to be in saddle, own the asset, and then we’ll have to assess potential expansion optionalities, offtake optionalities, techno-economics, a whole host of work before we’ll be in a position to press the button on the expansion post acquisition, right? So I think it will be a bit pre-mature to comment on that, yeah?

Rajesh Majumdar

No, no, appreciate it. Thank you, sir. My second question is, sir, on the O2 Power and KSK Mahanadi. Could you give us some color on the EBITDA that we can generate at, say, 1,800 megawatts of KSK and the full O2 Power capacity, say, FY ’27 or something, what can be the additional EBITDA from these two acquisitions?

Pritesh Vinay

No, Rajesh. I don’t think at this stage because it is…

Rajesh Majumdar

Some color on that maybe, yeah.

Pritesh Vinay

KSK, historical number is available last financial year in fiscal 2024, they had done an EBITDA of INR2,600 crores. So that is, in a way, public domain information. So happy to share that because there’s no breach of NDA obligations on that one. O2, we kind of have guided a steady-state EBITDA. When we go to a 2.3-gigawatt operational capacity, which is expected, say, in the middle of this year, then on an annualized run rate basis, that portfolio will generate about INR1,500 crores of EBITDA. There’s a particular slide we had put in the deck that was uploaded at the time of the O2 acquisition. So you will get that at the 2.3 gigawatts, a steady-state run rate is about INR1,500 crores. When it goes to the 4.7 gigawatts, the expected steady-state EBITDA run rate is about INR3,750 crores. So, beyond that, we’ll not be able to add anything else.

Rajesh Majumdar

Right, sir. And one small bookkeeping question. What was the merchant tariff in Q3?

Pritesh Vinay

So merchant tariff, we do not share, but you will be able to derive. Let me help you how to do that. In the total generation in the appendixes, you will see total and long-term differentiation, the gap is a short-term volume. There is an EBITDA bridge where we are talking about the EBITDA impact due to that. You know what the coal price indices, how they have moved. So you will be able to gross it up, yeah?

Rajesh Majumdar

Thank you, sir. Thank you.

Operator

Thank you. The next question comes from Sumit Kishore from Axis Capital. Please go ahead.

Sumit Kishore

Good evening. My first question is of the 7.8 gigawatts over and above the 10 gigawatts target for FY ’25 that you have PPAs for, how are you placed in terms of the transmission evacuation and land for these projects?

Sharad Mahendra

Yeah. Sumit, a very, I will say, relevant point because everyone is questioning about the connectivity and land, which the industry is facing as challenge. But we acted upon and majority of the capacity, the PPAs which we are trying, we are fully ready, whether it is land or connectivity. And to overcome the connectivity issue, the significant portion of this total 7.8 gigawatts is within the state, for the same state, through the STU connectivity, which is available in most of the states. So that was the step which we had started acting about nine months a year back. So that is the reason our readiness and we are absolutely certain that the 7.8 gigawatts of the PPA signed, these projects will be completed within the time frame as per the PPA terms and connectivity and land will not be

A challenge in the — both these cases.

Sumit Kishore

So, most of these projects will not require CTU?

Sharad Mahendra

Majority, wherever the CTUs, small capacities are there, where it is CTU, where it is available. But this 7.8 gigawatts is entirely locked in, in terms of connectivity and also the land. So there is no challenge in terms of land and connectivity for the 7.8 gigawatts of projects to be completed within the time frame as per the PPAs.

Sumit Kishore

Sir, my second question is more at an industry level. What are the emerging trends you are seeing in wind and solar sizing for FDRE projects with the evolving battery economics? How is it changing the sizing for wind and solar in FDRE projects?

Sharad Mahendra

Again, I will say a very good question in terms of when we say FDRE till now, what we have seen in last six months a small change which we are seeing, it is more of a better planning for the project to provide the right solution to the end buyer as per their requirements in FDRE that we were seeing in majority of the cases earlier, which was happening for a hybrid wind and solar maybe combined with the storage at normally single location, which was restricting the solutions.

Now, in fact, we also in the C&I space have signed wherein to optimize and take out the best of the generation and the lowest cost per unit of investment, that wind is in one state connected with CTU and solar is in a different state along with battery if required, or if it’s a hybrid, and providing the solution to the same customer. So, this is one case which we have seen from co-located to diversified hybrid solutions, along with the storage is one we are seeing.

Another thing which has been witnessed in the last six to eight months, if you have been monitoring the kind of bids which are coming, that with so much of solar capacity additions, the — and whatever capacity addition, country has seen about 20 gigawatts in maybe first nine months, 19 gigawatts to 20 gigawatts, 16 gigawatts is solar. The solution, despite a moderate growth of 4.5% during the evening peak hours or early morning peak hours, the demand/supply situation is going to be even more challenging. The demand will keep on growing. So with this, the solution of solar plus battery energy storage projects are coming up now, which has a two-pronged advantage. One is that solar during the day times and charging the battery and releasing during the evening peak hours when there is — the demand is more. And second is better utilization of the country’s grid infrastructure because solar project takes — blocks the capacity for 24 hours and only uses for eight hours. So, this is a better utilization of countries assets, also which are their transmission assets, and a solution for the peaking.

So, these are certain changes that we are seeing. Of course, states are now working very seriously towards the solution for peak hour requirements, which after five years from now, the gap is going to be significant even if there is a continuous 5% to 6% demand growth. For that pump storage for a longer solution, storage solution is again now taking due importance and preference and states are coming up with their bids for pump storage also.

So these are significant changes which we have noticed in last six months.

Sumit Kishore

Sure, sir. My final question on your energy storage projects, particularly on stand-alone BESS, SECI XV, and Group Captive. So, has there been any slowdown after the CERC order in your efforts to commission your SECI stand-alone project because it has had a merchant component? And how are the others progressing in terms of commissioning? And if you could give us some color on what kind of pricing you would have, or capex for the battery capacity that you create?

Sharad Mahendra

See, one is that there is no slowdown. A lot of bids are coming, people are participating, and battery energy storage for a short duration is the best solution right now, which is required fast. So this is one there is no slowdown. Apart from that, we will like, as I have told in my opening remarks, that this now case where the decision has been challenged. So, I don’t think, we have to remember that when anyone evaluates and compares that what was the price discovered during that time, during that project, which is now tariff adoption, has not been done and this is challenged by us. And what the tariff discovery is there today, today. It apparently looks very high, but we have to see see two significant difference in that project as compared to the current projects which are coming and which also have a good viability, that this was with a viability gap funding of more than maybe 40%-45% in terms of the tariff discovered which we have got.

And apart from that, this is a BOOT model in which after 12 years the asset gets transferred in that case. Now the bids which are coming is not on the BOOT model in most of the cases. So it is not a like-to-like comparison from what the today’s project cost is, what is the cost — tariff discovery which is there. So, this is what we would like to say in terms of the capex and all. These are very dynamic numbers. The tariffs which being discovered are based on — what is the design, what is the storage, what is the loading. So this is dynamic. So this is what I will like to mention for this what you just asked.

Sumit Kishore

Sure. So, you had mentioned on the previous call that 1 gigawatt-hour BESS will get commissioned by June ’25. So just wanted to check whether that plan would still be on track?

Sharad Mahendra

Because of this development, it may take maybe a few — depending on how fast the decision comes it may take maybe a few months here or there, that is all. We will be in a better position once this legal matter gets closed.

Sumit Kishore

Because the capacity can be fungible across your other…

Sharad Mahendra

Absolutely, absolutely, absolutely. These are all containerized solutions, and it is not at all possible. We have enough of order book within the Group Captive and other locations to use the same assets. So that is not at all a challenge.

Sumit Kishore

Sure. Thank you.

Operator

Thank you. [Operator Instructions]. The next question comes from the line of Nikhil Abhyankar from UTI Mutual Funds. Please go ahead.

Nikhil Abhyankar

Thank you, sir. Sir, my first question is regarding the Mytrah generation. Have we seen a dip in Q3? And was it related to machine availability or due to lower wind?

Sharad Mahendra

See, there is a slight dip in Mytrah generation, which is basically because of the wind speeds which were slightly lower than what was expected, but that is very temporary and short term. We don’t see any lasting impact of that. But machine availability wise, there was no challenge. The machine availability continues to remain at almost close to 98% to 99%. So machine availability is there. It is only the wind, which is there. 97% to 98% availability remains there.

Nikhil Abhyankar

Okay. And sir, after we announced our O2 acquisition, I think they won a SECI bid for FDRE VI for 200 megawatts x 4 hours and the tariff disclosure is almost 8.5. That project will also be transferred to us?

Sharad Mahendra

Once this happens, yes, definitely, yes, it is there.

Pritesh Vinay

Part of the platform.

Sharad Mahendra

It is part of the platform. So, 4.7 then will become 4.9-plus gigawatts.

Nikhil Abhyankar

Okay. And sir, just a final question on the capex. How much was done till nine months? And what do you expect the capex to be in FY ’26?

Pritesh Vinay

So, Nikhil, for the first nine months, the total capex that has been spent is about INR6,200 crores. And we are expecting to end the full year with close to INR10,000 crores. If you recall, earlier, we had said we were expecting a INR15,000 crores total capex for the year. But of course, the current batch of projects that we are planning to complete are getting completed. And we had anticipated a higher amount of investment in the organic future projects. But looking at the constraints that Sharad was earlier talking about from — and some of you have also raised questions about, which is a reality in the sector from connectivity, etc., point of view.

What we have done instead, as you would have seen by our strategic actions in the quarter is to press the pedal on the inorganic side, right? The idea is to continue to deliver growth at a certain CAGR. So, because organic is kind of seeming to be a bit challenging to scale up after considering everything, we have gone ahead and press the pedal on the inorganic route. And this also gives time for us from a better planning and taking the long lead time actions well in advance to maintain the organic growth trajectory going forward, yeah.

Nikhil Abhyankar

Understood. So, do we expect any kind of delays in renewable capacity additions for our 28 gigawatts of locked-in capacity because of the transmission constraints?

Pritesh Vinay

So, it’s the other way around, right? What we have actually publicly stated is we were aiming to be a 20-gigawatt generation company by 2030. We had shared this in, I think, 2023, May 2023 we had shared this with the market. Now you are seeing in front of you, there is already a — just shy of a 30-gigawatt platform and hopefully, we should be able to deliver all of this well before 2030, right? So clearly, there’s an acceleration of growth. And there will have to be calibration. There will have to be — because it is a block and tackle project by project, location by location. We are actually not quantified anything beyond 10 gigawatts on an annual basis. But if I were to just do a broad math assuming that at least by June quarter, if we are able to consummate both KSK and O2, plus our own hitting the 10-gigawatt mark, we will be a 14-gigawatt operating platform by June ’25, right, which is a few months from now. So — and then we’ll take it from there, right? When we come back with our annual fiscal year results, we would have gone through the business planning exercise for the next year, and we will be in a better position to give you an organic capacity accretion target for fiscal ’26. Yeah?

Nikhil Abhyankar

Sure, sir. Thank you and all the very best.

Pritesh Vinay

Thank you.

Operator

Thank you. The next question comes from Saket Yadav from India Capital. Please go ahead.

Saket Yadav

Hi. So, I have a couple of questions on KSK Mahanadi. We understand that there are lenders who still own 26% of the stake. So, I just wanted to understand that the bid you have placed is for the 100% stake or will that 26% still remain with the lenders?

Pritesh Vinay

No, no. 26% will stay with the lenders, but there is a put option with the lenders, which will get active after one year. And within one to five years, they have a right to exercise that put. And obviously, no lender has a strategic intent to remain a minority equity investor in a non-core business, right? So, their idea is to maximize their recovery and recoup all the losses, etc., of the past, right?

So, there is a plan. The first step is to get through the regulatory adjudication process of getting the asset in control, and then we will get into discussions with the lenders on the balance 26% stake.

Saket Yadav

Right. Understood. Thank you. And my next question is, again, on KSK Mahanadi. I wanted to understand that I read it somewhere that there are some INR3,000 crores to INR4,000 crores held with one of the units of KSK Mahanadi. And I wanted to know that, will that be absorbed by the company or will it be distributed to the lender?

Pritesh Vinay

No, no, no. See, the terms of the RFP when the IBC process commenced, was that whatever was the cash accrued, receivables, EBITDA generation, etc., all of that belongs to the lender. So any resolution applicant to put in their plans for consideration by the CoC took that into consideration, right, that you are only bothered as an applicant with how much of money you’re offering to both the financial creditors and the operational creditors. There was a specific scoring mechanism, and hence, as an objective, as a winning strategy, your idea is to maximize the score and work with that. So, whenever the plan gets adjudicated, till then — or, whenever the plan gets implemented or consummated, till then whatever accrues will go to the lenders. So, there should be no surprise on that front. Yeah?

Saket Yadav

Understood. Thank you. Congratulations on the acquisition, friends. All the best.

Pritesh Vinay

Thank you.

Operator

Thank you. The next question — before we take the next question, requesting participants to restrict their questions to two per participant. If you have any other follow-up questions, you may rejoin the queue. The next question comes from Swati Jhunjhunwala from JM Financial PMS. Please go ahead.

Swati Jhunjhunwala

Yeah. Hi. Thanks for taking my questions. Sir, first question is on the green hydrogen. So, we expected to commission it soon. Any idea you can give on the revenue and EBITDA that we can generate from this?

Pritesh Vinay

No, Swati, not at this stage, please. We’ll complete it, and as we have said at the stage of announcing this pilot project is that the modality that has been worked on is that we will get a 15% equity IRR on this project, which is to be amortized completely over a period of seven years. So that’s how the economics is going to work. So once the project gets completed, the project cost is frozen, basis that on a normative debt equity and underlying equity IRR. And that is how the tariff is going to be worked out.

But I mean, okay, when you look at our total balance sheet, even if that number materially changes, I’m sorry to say that’s going to be a rounding error, right?It’s a very small project. So, it is not going to materially move the needle either way. Yeah?

Swati Jhunjhunwala

Got it. Second is on the commissioning. So right now, we are close to 8.1 gigawatts and another 7.8 gigawatts under construction. Now if by June, we are commissioning another 1.8 gigawatts, making it 10 gigawatts, plus the 4 gigawatts of the acquisition, the balance is under construction, if you could give even a broad split between FY ’26 and ’27, that would be great.

Pritesh Vinay

I just said a few minutes ago in response to another question that when we come back in the month of May with the annual results, having gone through an annual business planning exercise, we will be able to give an FY ’26 capacity addition guidance and then the balance will be basic arithmetic for you.

Swati Jhunjhunwala

Understood. All right. Thanks.

Operator

Thank you. The next question comes from Samarth Khandelwal from ICICI Securities. Please go ahead.

Samarth Khandelwal

Hello. Am I audible?

Sharad Mahendra

Yes.

Samarth Khandelwal

Yes, sir. Firstly, congratulations on the KSK Mahanadi acquisition. Secondly, sir, my question is on the battery energy storage system front. If I am supposed to how do I read a 250 megawatts by 500 megawatt-hour battery project? In terms of how much time would it take for the solar project to charge that amount of battery, how much time would we be able to supply and how much units would it be able to supply to the customer? What would be the battery life? How much would be the capex per megawatt-hour basis, if you could help me with that? Thank you.

Sharad Mahendra

See, we have to understand that if we are talking of 250 megawatts of battery energy storage capacity with the 2-hour discharge means 250 x 2, which is 500 megawatt-hour. When we convert it into energy and assuming that we are charging it with solar, it’s a solar plus or any kind of input energy, we have to assume that whatever this 500 megawatt-hour discharge is there. Maybe there is an efficiency loss when the input energy and the output energy depending on the battery design, how you design, how efficiently maybe 15%, 18%, 20%, whatever incremental energy for charging, which is required. So out of 100 maybe 120 is the input or 115 or maybe the output will be 100, that is the ballpark.

In terms of battery life, battery life is something that there is — as per the PPA term, the project is designed in such a way that the minimum availability of the battery is always there. So normally you can use the word repowering of the battery maybe once in four to five years, which is part of the capex depending on the requirement is done to maintain the output. But the benchmark is that after 12 years, mostly most of the storage bids which have come is for 12 years, after 12 years, the battery life of at least 70% is available even if we are not doing the repowering. And you are allowing the normal battery decay, then also after 12 years, the 70% of the battery life is still there in energy terms. So this is what I say.

Capex number, as I told you, depends on a lot of factors. Straightaway giving a capex number is a challenge because there are lot many factors which are variable in terms of whether related to connectivity, land and everything. So, this is the next thing you can say that 70% of the battery life is there after 12 years.

Samarth Khandelwal

So, we would be using lithium type of or sodium type of battery? And secondly, we would be charging the customer based on the number of units supplied or how much the solar generates to charge that amount of battery?

Sharad Mahendra

See, again, it depends on the bid design. Mostly, if it is a storage project alone it is not a unit, it is a rental model, lease model, that per megawatt, per month. If it is 250 megawatts for two hours, then the bid normally asked for that it is 250 megawatts capacity, so per megawatt, per month is the rental which is there, which is assured. Only thing is that the plant availability is to be ensured as per the terms.

If it is a battery, there are some cases in which it is, in energy terms also some bids are there, wherein combined with solar and evening discharge of two hours of battery and the number of units of what minimum is required during evening, then it is per-unit bids also which are there. So it is depending on the bid terms, which is — it is either rental model. But majority are rental models.

Pritesh Vinay

And Samarth, to answer your other part of your question, I mean, so far, we are not aware of sodium batteries being used for commercial large scale operations. So, I mean our limited understanding is that it’s only lithium-ion batteries.

Operator, can we make that the last question, please? We have — or, maybe we can take one more question, yeah? Because Sharad and I have to rush into

Something else. Yeah?

Operator

Sure. Thank you.

Pritesh Vinay

Let’s take one last question, please.

Operator

Sure. We’ll take one last question from the line of Ritwik Sheth from One Up. Please go ahead.

Ritwik Sheth

Yeah. Hi. Good evening, sir. Sir, actually, my question is a clarification. Earlier, you mentioned in the call the O2 acquisition, the 2.4 gigawatts, which is under development, will require a capex of INR13,000 crores. Did I hear it right?

Pritesh Vinay

Yes. So, you’re right, Ritwik. And you don’t have to rely on hearing or our speaking skills. My request is if you can go to our website or look at the stock exchange filings, there was a presentation that was made at the time of O2 Power acquisition in the last week of December. And there are two tables on one particular slide where you will get all the numbers linked to that, yeah. There’s a INR13,000 crores to INR14,000 crores expected capex. That was a balance of 2.4 gigawatts.

Ritwik Sheth

Got it. And just on the KSK acquisition, what would be the pending capex which will be required to do to operationalize the balance 1.8 gigawatts?

Sharad Mahendra

See, as I said earlier also that we will be coming out with the numbers when the process gets completed. But while doing the due diligence, as I said earlier in my opening remarks also, that the total plant capacity once fully operational is 3.6 gigawatts, and 50% is operational. But balance of the plant, most of the balance of the plant is ready for entire 3,600 megawatts, whether it is the transmission evacuation line or whether it is the water pipeline. And even there are three more units which have become. One of the units more than 40% of the work is complete. Balance other two units also part work is complete. So it will be at a significantly lower cost per megawatts capex at which the plant will be fully operational then the benchmark greenfield cost for 1.8 gigawatts.

So this is what we can say, giving the exact numbers, maybe at the right time, we will come back.

Ritwik Sheth

Okay. Sure. Thank you and all the best, sir.

Sharad Mahendra

Thank you.

Operator

Thank you. Ladies and gentlemen, I now hand the conference over to the management for closing comments.

Sharad Mahendra

Thank you, everyone. I think it has — thanks for being with us during this quarter three. And as I have said in my opening remarks, we see the things to be better in the coming year with what we see, expect and we are reading that maybe more of government spend and also the private investment likely to increase now, which will definitely have a positive impact on the power sector also.

Thank you very much for being with us.

Pritesh Vinay

And in case there are any follow-ups, please feel free to get in touch with our IR team. Thank you very much.

Operator

[Operator Closing Remarks]